What are the requirements of the Federal Implementation Plans (FIPs) relating to ozone season emissions of nitrogen oxides from the Cement and Concrete Product Manufacturing Industry?

§ 52.42 What are the requirements of the Federal Implementation Plans (FIPs) relating to ozone season emissions of nitrogen oxides from the Cement and Concrete Product Manufacturing Industry?

(a) Definitions. All terms not defined in this paragraph (a) shall have the meaning given to them in the Act and in subpart A of 40 CFR part 60.

Affected unit means a cement kiln meeting the applicability criteria of this section.

Cement kiln means an installation, including any associated pre-heater or pre-calciner devices, that produces clinker by heating limestone and other materials to produce Portland cement.

Cement plant means any facility manufacturing cement by either the wet or dry process.

Clinker means the product of a cement kiln from which finished cement is manufactured by milling and grinding.

Operating day means a 24-hour period beginning at 12:00 midnight during which the kiln produces clinker at any time.

(b) Applicability. You are subject to the requirements of this section if you own or operate a new or existing cement kiln that emits or has the potential to emit 100 tons per year or more of NOX on or after August 4, 2023, and is located within any of the States listed in § 52.40(c)(2), including Indian country located within the borders of any such State(s). Any existing cement kiln with a potential to emit of 100 tons per year or more of NOX on August 4, 2023, will continue to be subject to the requirements of this section even if that unit later becomes subject to a physical or operational limitation that lowers its potential to emit below 100 tons per year of NOX.

(c) Emissions limitations. If you are the owner or operator of an affected unit, you must meet the following emissions limitations on a 30-day rolling average basis during the 2026 ozone season and in each ozone season thereafter:

(1) Long wet kilns: 4.0 lb/ton of clinker;

(2) Long dry kilns: 3.0 lb/ton of clinker;

(3) Preheater kilns: 3.8 lb/ton of clinker;

(4) Precalciner kilns: 2.3 lb/ton of clinker; and

(5) Preheater/Precalciner kilns: 2.8 lb/ton of clinker.

(d) Testing and monitoring requirements. (1) If you are the owner or operator of an affected unit you must conduct performance tests, on an annual basis, in accordance with the applicable reference test methods of 40 CFR part 60, appendix A-4, any alternative test method approved by the EPA as of June 5, 2023, under 40 CFR 59.104(f), 60.8(b)(3), 61.13(h)(1)(ii), 63.7(e)(2)(ii), or 65.158(a)(2) and available at the EPA's website (https://www.epa.gov/emc/broadly-applicable-approved-alternative-test-methods), or other methods and procedures approved by the EPA through notice-and-comment rulemaking. The annual performance test does not have to be performed during the ozone season. You must calculate and record the 30-operating day rolling average emissions rate of NOX as the total of all hourly emissions data for a cement kiln in the preceding 30 days, divided by the total tons of clinker produced in that kiln during the same 30-operating day period, using equation 1 to this paragraph (d)(1):