Visibility protection.

§ 52.1183 Visibility protection.

(a) [Reserved]

(b) Regulation for visibility monitoring and new source review. The provisions of § 52.28 are hereby incorporated and made a part of the applicable plan for the State of Michigan.

(c) [Reserved]

(d) Regional Haze. The requirements of section 169A of the Clean Air Act are not met because the regional haze plan submitted by Michigan on November 5, 2010, does not include fully approvable measures for meeting the requirements of 40 CFR 51.308(d)(3) and 51.308(e) with respect to emissions of NOX and SO2 from electric generating units. EPA has given limited approval and limited disapproval to the plan provisions addressing these requirements.

(e) Measures Addressing Limited Disapproval Associated With NOX. The deficiencies associated with NOX identified in EPA's limited disapproval of the regional haze plan submitted by Michigan on November 5, 2010, are satisfied by § 52.1186.

(f) Measures Addressing Limited Disapproval Associated With SO2. The deficiencies associated with SO2 identified in EPA's limited disapproval of the regional haze plan submitted by Michigan on November 5, 2010, are satisfied by § 52.1187.

(g) The requirements of section 169A of the Clean Air Act are not met because the regional haze plan submitted on November 5, 2010, does not meet the best available retrofit technology requirements of 40 CFR 51.308(e) with respect to emissions of NOX and SO2 from Saint Marys Cement in Charlevoix and NOX from Escanaba Paper Company in Escanaba. These requirements for these two facilities are satisfied by 40 CFR 52.1183(h) and 40 CFR 52.1183(i), respectively.

(h)

(1) For the 30-day period beginning January 1, 2017, and thereafter, Saint Marys Cement, or any subsequent owner or operator of the Saint Marys Cement facility located in Charlevoix, Michigan, shall not cause or permit the emission of oxides of nitrogen (expressed as NO2) to exceed 2.80 lb per ton of clinker as a 30-day rolling average.

(2) For the 12-month period beginning January 1, 2017, and thereafter, Saint Marys Cement, or any subsequent owner or operator of the Saint Marys Cement facility located in Charlevoix, Michigan, shall not cause or permit the emission of NOX (expressed as NO2) to exceed 2.40 lb per ton of clinker as a 12-month average.

(3) Saint Marys Cement, or any subsequent owner or operator of the Saint Marys Cement facility located in Charlevoix, Michigan, shall not cause or permit the emission of SO2 to exceed 7.50 lb per ton of clinker as a 12-month average.

(4) Saint Marys Cement, or any subsequent owner or operator of the Saint Marys Cement facility located in Charlevoix, Michigan, shall operate continuous emission monitoring systems to measure NOX and SO2 emissions from its kiln system in conformance with 40 CFR part 60 appendix F procedure 1.

(5) The reference test method for assessing compliance with the limit in paragraph (h)(1) of this section shall be use of a continuous emission monitoring system operated in conformance with 40 CFR part 60, appendix F, procedure 1. A new 30-day average shall be computed at the end of each calendar day in which the kiln operates, based on the following procedure: First, sum the total pounds of NOX (expressed as NO2) emitted during the operating day and the previous twenty-nine operating days, second, sum the total tons of clinker produced during the same period, and third, divide the total number of pounds by the total clinker produced during the thirty operating days.

(6) The reference test method for assessing compliance with the limit in paragraphs (h)(2) and (h)(3) of this section shall be use of a continuous emission monitoring system operated in conformance with 40 CFR part 60, appendix F, procedure 1. A new 12-month average shall be computed at the end of each calendar month, based on the following procedure: First, sum the total pounds of NOX or SO2, as applicable, emitted from the unit during the month and the previous eleven calendar months, second, sum the total tons of clinker production during the same period, and third, divide the total number of pounds of emissions of NOX or SO2, as applicable, by the total clinker production during the twelve calendar months.

(7) Recordkeeping. The owner/operator shall maintain the following records for at least five years:

(i) All CEMS data, including the date, place, and time of sampling or measurement; parameters sampled or measured; and results.

(ii) All records of clinker production, which shall be monitored in accordance with 40 CFR 60.63.

(iii) Records of quality assurance and quality control activities for emissions measuring systems including, but not limited to, any records required by 40 CFR part 60, appendix F, Procedure 1.

(iv) Records of all major maintenance activities conducted on emission units, air pollution control equipment, CEMS and clinker production measurement devices.

(v) Any other records required by 40 CFR part 60, subpart F, or 40 CFR part 60, appendix F, procedure 1.

(8) Reporting. All reports under this section shall be submitted to Chief, Air Enforcement and Compliance Assurance Branch, U.S. Environmental Protection Agency, Region 5, Mail Code AE–17J, 77 W. Jackson Blvd., Chicago, IL 60604–3590.

(i) The owner/operator shall submit quarterly excess emissions reports for SO2 and NOX BART limits no later than the 30th day following the end of each calendar quarter. Excess emissions means emissions that exceed the emissions limits specified in paragraph (h)(1), (h)(2), and (h)(3) of this section. The reports shall include the magnitude, date(s), and duration of each period of excess emissions, specific identification of each period of excess emissions that occurs during startups, shutdowns, and malfunctions of the unit, the nature and cause of any malfunction (if known), and the corrective action taken or preventative measures adopted.

(ii) Owner/operator of each unit shall submit quarterly CEMS performance reports, to include dates and duration of each period during which the CEMS was inoperative (except for zero and span adjustments and calibration checks), reason(s) why the CEMS was inoperative and steps taken to prevent recurrence, and any CEMS repairs or adjustments.

(iii) The owner/operator shall also submit results of any CEMS performance tests required by 40 CFR part 60, appendix F, Procedure 1 (Relative Accuracy Test Audits, Relative Accuracy Audits, and Cylinder Gas Audits).

(iv) When no excess emissions have occurred or the CEMS has not been inoperative, repaired, or adjusted during the reporting period, such information shall be stated in the quarterly reports required by paragraphs (h)(7)(i) and (ii) of this section.

(i) Escanaba Paper Company, or any subsequent owner or operator of the Escanaba Paper Company facility in Escanaba, Michigan, shall meet the following requirements and shall not cause or permit the emission of NOX (expressed as NOX) to exceed the following limits:

(1) For Boiler 8, designated as EU8B13, a rolling 30-day average limit of 0.35 lb per MMBTU.

(2) A continuous emission monitoring system shall be operated to measure NOX emissions from Boiler 8 in conformance with 40 CFR part 60, appendix F.

(3) The reference test method for assessing compliance with the limit in paragraph (i)(1) of this section shall be a continuous emission monitoring system operated in conformance with 40 CFR part 60, appendix F. A new 30-day average shall be computed at the end of each calendar day in which the boiler operated, based on the following procedure: first, sum the total pounds of NOX emitted from the unit during the operating day and the previous twenty-nine operating days, second sum the total heat input to the unit in MMBTU during the same period, and third, divide the total number of pounds of NOX emitted by the total heat input during the thirty operating days.

(4) For Boiler 9, also identified as EU9B03, a limit of 0.27 lb per MMBTU.

(5) The reference test method for assessing compliance with the limit in paragraph (i)(4) of this section shall be a test conducted in accordance with 40 CFR part 60, appendix A, Method 7.

(6) Recordkeeping. The owner/operator shall maintain the following records regarding Boiler 8 and Boiler 9 for at least five years:

(i) All CEMS data, including the date, place, and time of sampling or measurement; parameters sampled or measured; and results.

(ii) All stack test results.

(iii) Daily records of fuel usage, heat input, and data used to determine heat content.

(iv) Records of quality assurance and quality control activities for emissions measuring systems including, but not limited to, any records required by 40 CFR part 60, appendix F, Procedure 1.

(v) Records of all major maintenance activities conducted on emission units, air pollution control equipment, and CEMS.

(vi) Any other records identified in 40 CFR 60.49b(g) or 40 CFR part 60, appendix F, Procedure 1.

(7) Reporting. All reports under this section shall be submitted to the Chief, Air Enforcement and Compliance Assurance Branch, U.S. Environmental Protection Agency, Region 5, Mail Code AE–17J, 77 W. Jackson Blvd., Chicago, IL 60604–3590.

(i) Owner/operator of Boiler 8 shall submit quarterly excess emissions reports for the limit in paragraph (i)(1) no later than the 30th day following the end of each calendar quarter. Excess emissions means emissions that exceed the emissions limit specified in paragraph (i)(1) of this section. The reports shall include the magnitude, date(s), and duration of each period of excess emissions, specific identification of each period of excess emissions that occurs during startups, shutdowns, and malfunctions of the unit, the nature and cause of any malfunction (if known), and the corrective action taken or preventative measures adopted.

(ii) Owner/operator of Boiler 8 shall submit quarterly CEMS performance reports, to include dates and duration of each period during which the CEMS was inoperative (except for zero and span adjustments and calibration checks or when Boiler 8 is not operating), reason(s) why the CEMS was inoperative and steps taken to prevent recurrence, and any CEMS repairs or adjustments.

(iii) Owner/operator of Boiler 8 shall also submit results of any CEMS performance tests required by 40 CFR part 60, appendix F, procedure 1 (Relative Accuracy Test Audits, Relative Accuracy Audits, and Cylinder Gas Audits).

(iv) When no excess emissions have occurred or the CEMS has not been inoperative, repaired, or adjusted during the reporting period, such information shall be stated in the quarterly reports required by paragraph (i)(7) of this section.

(v) Owner/operator of Boiler 9 shall submit reports of any compliance test measuring NOX emissions from Boiler 9 within 60 days of the last day of the test. If owner/operator commences operation of a continuous NOX emission monitoring system for Boiler 9, owner/operator shall submit reports for Boiler 9 as specified for Boiler 8 in paragraphs (i)(7)(i) to (i)(7)(iv) of this section.