Phase I unit allowance surrender.

§ 72.92 Phase I unit allowance surrender.

(a) Annual compliance certification report. If a Phase I unit's adjusted utilization for the calendar year in Phase I under § 72.91(a) is greater than zero, then the designated representative shall include in the annual compliance certification report the number of allowances that shall be surrendered for adjusted utilization using the formula in paragraph (c) of this section and the calculations that were performed to obtain that number.

(b) Other submissions. (1) [Reserved]

(2)

(i) If any Phase I unit in a dispatch system is governed during the calendar year by an approved reduced utilization plan relying on sulfur-free generation, then the designated representatives of all affected units in such dispatch system shall jointly submit, within 60 days of the end of the calendar year, a dispatch system data report that includes the following elements in a format prescribed by the Administrator:

(A) The name of the dispatch system as reported under § 72.33;

(B) The calculation of “percentage change in dispatch system sales” under § 72.91(a)(3)(iii)(C);

(C) A certification that each designated representative will use this figure, as appropriate, in its annual compliance certification report and will submit upon request the data supporting the calculation; and

(D) The signatures of all the designated representatives.

(ii) If any Phase I unit in a dispatch system has adjusted utilization greater than zero for the calendar year, then the designated representatives of all Phase I units in such dispatch system shall jointly submit, within 60 days of the end of the calendar year, a dispatch system data report that includes the following elements in a format prescribed by the Administrator:

(A) The name of the dispatch system as reported under § 72.33;

(B) The calculation of “percentage change in dispatch system sales” under § 72.91(a)(3)(iii)(C);

(C) The calculation of “dispatch system adjusted utilization” under paragraph (c)(2)(i) of this section;

(D) The calculation of “dispatch system aggregate baseline” under paragraph (c)(2)(ii) of this section;

(E) The calculation of “fraction of generation within dispatch system” under paragraph (c)(2)(v)(A) of this section;

(F) The calculation of “dispatch system emissions rate” under paragraph (c)(2)(v)(B) of this section;

(G) The calculation of “fraction of generation from non-utility generators” under paragraph (c)(2)(v)(C) of this section;

(H) The calculation of “non-utility generator average emissions rate “ under paragraph (c)(2)(v)(F) of this section;