Are there any additional contract administration requirements?

§ 33.302 Are there any additional contract administration requirements?

(a) A recipient must require its prime contractor to pay its subcontractor for satisfactory performance no more than 30 days from the prime contractor's receipt of payment from the recipient.

(b) A recipient must be notified in writing by its prime contractor prior to any termination of a DBE subcontractor for convenience by the prime contractor.

(c) If a DBE subcontractor fails to complete work under the subcontract for any reason, the recipient must require the prime contractor to employ the six good faith efforts described in § 33.301 if soliciting a replacement subcontractor.